Final countdown to compliance with the BWM Convention

With the Ballast Water Management Convention entering into force on 8 September, DNV GL would like to remind you of a few last-minute but important issues.

Relevant for owners and managers, design offices, shipyards, suppliers and flag states.

1. Actions needed before 8 September 2017

The entry into force date of the BWM convention is 8 September 2017. By this date all vessels subject to the convention must be in compliance with the D-1 (exchange standard). To quickly identify the steps customers may have to take before 8 September, DNV GL has prepared the following examples, with recommended actions:

Scenario A – vessel status: 

BWM_scenario A

Action: Vessel in compliance – No further actions needed

Scenario B – vessel status: 

BWM scenario B

Action: 
Step 1: Generate Ballast Water Management Plan (BWMP) quickly and efficiently with DNV GL's free-to-use web application BWMP Generator.

Step 2: Submit the BWMP for approval to: bwmp.exchange@dnvgl.com. For BWMPs received in the last 2 weeks before 8 September, a certificate will be issued in accordance with BWM.2/Circ.40 including the provision that the BWMP is to be approved and initial survey concluded before 8 December 2017. (Circ.40 allows a grace period of 3 months to complete the initial survey and certification after the entry into force date, see below). 

Scenario C – vessel status: 

BWM scenario C

Action: 
If you are not able to perform an initial survey before 8 September 2017, please request DNV GL to issue a certificate in accordance with BWM.2/Circ.40. The certificate will be issued with the provision that the initial survey is concluded before 8 December 2017. Requests to be submitted to: bwmp.exchange@dnvgl.com.

2. Office based D-1 initial surveys and position of flags

DNV GL has been authorized to issue the BWM D-1 certificate without a physical survey carried out on board by the following flag state administrations: Antigua and Barbuda, Bahamas, Cyprus, Denmark, Germany, Latvia, Marshall Islands, Malta, Netherlands and Norway.

This is subject to certain conditions, including a declaration by the vessel’s Master regarding the availability of an approved BWM plan and record book on board the vessel. This option may only be given to vessels flying one of the above flags if no scheduled or occasional survey is planned prior to 8 December 2017 - fully utilising the period of grace granted by the IMO BWM.2/Circ. 40. (please see above).

If the conditions listed above are met, an e-mail requesting the initial BWM D-1 office based survey and certification including a scanned copy of the declaration by the Master should be sent to bwmp.exchange@dnvgl.com. For more information on this, please contact your local DNV GL office. 

3. D-2 compliance

The MEPC (71) meeting in early-July reached a compromise on compliance dates for the ballast water D-2 standard (installation date).

  • All ships with a keel laying after 8 September 2017 must comply with the D-2 standard on delivery. 
  • Existing ships must, in general, comply with the D-2 standard by the first IOPP renewal after 8 September 2019. 

Ships to which the IOPP renewal survey does not apply (generally ships below 400 GT and oil tankers below 150 GT) with a keel laying before the 8 September 2017 must be in compliance with the D-2 standard no later than 8 September 2024.

Recommendations

All DNV GL customers are advised to avoid last-minute preparation, and to carefully examine and consider their ship’s individual IOPP renewal dates to ensure compliance. If you are uncertain about what to do, please contact your flag or your local DNV GL office. 

References

DNV GL key resource page on Ballast Water Management, including the new “D-2 Calculator” to verify the required compliance dates for each vessel. 

Previously issued Technical and Regulatory News from DNV GL:

Contact
  • For customers: DATE – Direct Access to Technical Experts via My DNV GL
  • Otherwise: Use our office locator to find the nearest DNV GL maritime office
24 February 2020

IMO Sub-Committee on Pollution Prevention and Response

The 7th session of the IMO’s Sub-Committee on Pollution Prevention and Response (PPR) was held in London from 17 to 21 February 2020. PPR 7 finalized guidelines for Exhaust Gas Cleaning Systems (EGSC – scrubbers), developed a basis for work to determine the impact of EGCS discharge water on the environment, drafted regulations for prohibiting the use and carriage of HFO as fuel in the Arctic, and revised the guidance on ballast water system commissioning.

  • Maritime
10 February 2020

IMO Sub-Committee on Ship Design and Construction

The 7th session of IMO’s Sub-Committee on Ship Design and Construction (SDC) was held in London from 3 to 7 February 2020. SDC 7 finalized the interim guidelines on the second-generation intact stability criteria, clarified the requirements to watertight integrity on passenger ships and cargo ships, developed mandatory provisions for OSVs and other cargo ships carrying more than 12 industrial personnel, and finalized safety guidelines for fishing vessels and pleasure yachts operating in polar waters.

  • Maritime
27 January 2020

IMO Sub-Committee on navigation, communications and search and rescue

This statutory news provides an update from the 7th session of the IMO’s Sub-Committee on Navigation, Communications and Search and Rescue (NCSR), held in London from 15 to 24 January 2020. NCSR 7 agreed to recognize the Indian Regional Navigation Satellite System (IRNSS) for the provision of positioning, navigation and timing services, and finalized draft SOLAS amendments for the modernization of the Global Maritime Distress and Safety System (GMDSS).

  • Maritime
View all